这是我的version,哈哈,大家多交流:)
摘要
Abstract
本文为宿迁至靳桥段249省道老路改善工程,总共分为十章,包括工程概况与特点、施工的方案比选、概预算、施工总体部署、施工总进度计划、施工总平面控制及交通组织、工程质量的保证、安全环境、环境保护与文明施工、安全劳保技术措施。
Ten sections will be presented in this paper of the betterment works in dart S249 from Suqian to Jinqiao,including the project profile and character, working scheme comparison,budget estimate,construction master plan,construction schedule, general floor plan of construction and traffic operation,construction quality control, safety, environmental conservation and civilized construction, measure of working security guarantee.
建设的目的是为了满足S249省道与宁宿徐高速相连后庞大的交通流量,以及下穿盐徐高速后的贯通,本项目采用一级公路标准,采用双向六车道,设计速度为100km/h以满足下盐徐高速后往靳桥方向三岔口上宁宿徐高速的稳定、舒适的交通。
To meet dart S249's soaring traffic flow,which will be numerous after dart S249 connects with NingXu highway and YanXu highway, this construction is proposed. With the application of A road standard,two-way and six-lane transveral profile and 100 km/h design speed,the project is capable to provide stable and comfortable traffic condition from YanXu highway to NingXiuXu highway.
本249省道改建工程主要位于宿迁三棵树镇的中心,交通流量比较大,施工有一定难度,周边老房屋密集复杂交错相连,只能采取半幅施工方法,需要设计临时便道。本工程分为个施工段:三棵树桥与靳桥拓宽改造、埠子镇的道路新建段、三棵树镇水泥路的拓宽施工、快速路改造施工、宿迁南外环分离式立交桥下的施工。本工程工期比较短,时间比较紧。
在本次设计中逐步掌握工程开工前的施工准备,以及工程施工中的施工组织设计,了解各分项工程的施工工艺。
The site of S249 betterment works project locates at the centre of SanKeshu township in XiuQian with a complicated condition:numerous traffic flow and high density of houses. Half-way construction and temperary pioneer roads will be applicated in the project to come across the problem. The construction of this project is divided into five sections: broadening of Sankeshu bridge and Jin bridge, new road building in Zhouzi township, broadening of cement road in Sankeshu township, reconstruction of expressway, construction beneath the devided interchange to the Southern Xiuqian, with a tight schedule.
在本次设计中逐步掌握工程开工前的施工准备,以及工程施工中的施工组织设计,了解各分项工程的施工工艺。
The designer has grasped the preparation of construction and the construction management plan,and been familiar with the technique of each subdivisional work gradually during the process.
关键字:施工组织设计,施工方法,进度,安全,质量
Key words: construction management plan, construction methods, schedule, safety, quality |